Solar Panel Installation Timeline

The actual installation of solar panels on your home typically takes between one and three days. This part of the process involves mounting panels, connecting wiring, and configuring the system to your home’s electrical setup. 

That’s just the hands-on stage and there’s a bit more involved from start to finish. From your first consultation to your system going live, the full process can take several weeks. So how long does it take to install solar panels from start to finish? Here’s a breakdown of each stage to help you plan with confidence. 

1. Initial Consultation and Site Assessment (1 to 2 weeks) 

Every solar project starts with a conversation. When you contact the team at Auswell Energy, they begin by discussing your energy needs and reviewing recent electricity usage. A qualified technician then visits your home to assess your roof space, orientation, shading, and any other factors that may impact performance. 

During this phase, you will also discuss your budget and any preferences for system type or brand. 

Timeframe: Around one to two weeks, depending on scheduling. 

2. System Design and Proposal (1 to 2 weeks) 

After the site assessment, Auswell Energy designs a custom solar system tailored to your energy goals and home layout. You will receive a detailed proposal outlining the system’s size, estimated output, financial projections, and all costs involved. 

This is also a great opportunity to ask about battery storage options. You can explore Auswell’s battery storage solutions to future-proof your energy use. 

Timeframe: One to two weeks. 

START SAVING WITH SOLAR

Take control of your power bills! Contact us for a Free Quote

3. Permits, Approvals, and Grid Applications (2 to 6 weeks) 

Before any physical work begins, your installer must obtain permits from local authorities and approval from your electricity retailer or distributor. This step ensures your system is legally compliant and eligible for connection to the grid. 

The good news is, Auswell Energy manages this entire process for you. Their experience working with councils and energy providers helps keep things moving. 

Timeframe: Two to six weeks, depending on council and utility turnaround times. 

4. Equipment Procurement and Scheduling (1 to 2 weeks) 

Once the green light is received, Auswell Energy orders your system components and books in your installation. Availability of specific panels or inverters can impact timing, but Auswell works with trusted suppliers to ensure prompt delivery. 

Timeframe: One to two weeks. 

5. Installation (1 to 3 days) 

This is the part most homeowners look forward to. A team of accredited solar installers arrives at your property and begins work. They will mount your solar panels, install the inverter, connect the system to your switchboard, and complete all electrical configurations. 

If you choose to include a battery, this is installed at the same time. Auswell’s installers take care to minimise disruption and leave your property clean and tidy. 

Timeframe: Typically one to three days. 

6. Final Inspection and Grid Connection (1 to 3 weeks) 

Once the installation is complete, a final inspection may be required by a local authority or electrical inspector. After this, your energy retailer completes the grid connection. This step is essential for enabling exports to the grid and activating any applicable feed-in tariffs. 

Timeframe: One to three weeks. 

Factors That Can Affect Your Timeline 

While Auswell Energy does everything they can to keep things on track, a few variables may affect how quickly your system is up and running: 

  • Size and complexity of your solar system
  • Roof material or height
  • Extreme weather or safety delays
  • Council or utility response times
  • Equipment stock levels

Why Homeowners Choose Auswell Energy 

With Auswell Energy, you get more than just a solar installer. You get a dedicated partner who guides you from your first question through to turning the system on. Their team handles the paperwork, installation, inspections, and connection process from start to finish. 

You can also explore Auswell’s solar finance options if you want to get started without a large upfront investment. 

If you are ready to install solar and want a trusted team by your side, contact Auswell for a free quote and consultation. 

Note: These timeframes are estimates and may vary based on your location, system configuration, and local regulations. 

Frequently Asked Questions 

Can I use my solar panels immediately after installation? 
Not quite. Your system must first pass final inspection and be connected to the grid by your energy retailer. Once that step is complete, your solar panels can begin generating and exporting power. 

Do I need to be home for the installation? 
Yes, someone should be home to allow access to the switchboard and ensure clear communication with the installers. The Auswell team will coordinate timings with you directly. 

What happens if it rains on the scheduled installation day? 
Safety comes first. If the weather poses a risk to workers or system integrity, the installation will be rescheduled for the earliest possible date. 

Still have questions? Contact Auswell for personalised advice about going solar. 

SHARE THIS ON:

Facebook
Twitter
LinkedIn

Contact Auswell Energy!

Get in contact with Auswell Energy for a FREE consultation today! Just call us  or send us your enquiries.

FIND US ON:

Scroll to Top

WIN A FREE
SOLAR SYSTEM

Enter the draw to win!

*CONDITIONS:

  • 1 x SolarEdge 5kw Inverter
  • 21 x 310w Trina Solar Panels
  • Installation
  • Racking Included
  • Can’t be sold for Cash
  • Drawn Monday, 2nd March 2020

How much
can you save?

Estimate your system size, cost and savings.*

  • PV-icon Created with Sketch.
    Recommended system size
    kw
  • cost-icon Created with Sketch.
    Estimated system cost
  • piggy-icon Created with Sketch.
    Anticipated annual savings
    $
  • piggy-icon Created with Sketch.
    Anticipated system payback
    years
Book a Free Consultation